Skip to main content

Dry Docking - Part 2

SCOPE OF DRY DOCK WORK: 

The list of jobs to be carried out during dry docking are as under:

  1. BOTTOM INSPECTION AND CORRECTIVE ACTION AS RECOMMENDED BY CLASSIFICATION SOCIETY SURVEYOR.                                                                                                                                                                               The first visit of the surveyor on the ship. This inspection is carried out and the dock is dry with the ship's bottom scraped free of barnacle growth. This inspection is usually carried out during daylight hours especially after daybreak. In case the ship docks late in the night the following morning. The attending superintendent along with Master C/E, C/O & 2/O will enter the dock and go around the ship from forward to aft. The yard attending repair manager will also be present during this inspection.                                                                       This general inspection and any noticeable defects will be further examined and corrective action taken accordingly. Normally the defects noticed are of two types,                     (a) Dents which are deep and spread over a small area are further examined internally to note the extent of damages to stiffeners fitted internally so that the damaged portion of the stiffeners are renewed along with the dented shell plating.                                                                                                            (b) Areas of shell plating which have eroded and wasted badly are to be gauged and if needed renewed to the extent required.            
  2. BOTTOM PREPARATION AND PAINTING AS PER COMPANY'S PAINTING SPECIFICATIONS                                                                                                                              This is the first objective in drydocking commences on the first day and continues till almost to the last day in dry dock. On the first day, the areas requiring grit blasting are decided by the superintendent in consultation with the paint suppliers technical officer and yard's painting department manager. The areas where heavy grit blasting are required on an average are as follows:                                                                        (a)Topside about 40% of the total top side area. After grit blasting two coats of primer paint put each coat 30 microns.                                                                                                        (b) The boot top about 60% the total belt area consisting of the wind and weather strakes extending from summer load line to LWL. After grit blasting to apply two coats of primer paint each coat 40 microns thick.                                                                                                                                                            (c) On the bottom side the grit blasting area is negligible and at the most does not exceed about 5%. Two coats of primer paint must be applied to the blasted areas.                                                                                                                                              (d) The full painting specification now as an example is as follows                                                                             Topside- Two coats primer paint each coat 40 microns thick and two coats finish paint 40 microns thick, each coat.         Boot Top- Two coats primer paint each coat 40 microns thick, two coats finish paint, each coat 40 microns thick. Antifouling paint one coat each.                                                     Bottom- Two coat primer paint 40 microns thick each coat. Two coats finish paint 40 microns thick each coat. One coat antifouling paint 40 microns thick.                                                                                                                                         During the painting process, the paint suppliers technical officer checks the coating thickness using a paint thickness gauge which is a strip of plating about 3mm thick with marking which whilst scrapping the half-dried paint indicates the thickness by the thickness noted on the plate gauge. The paint is applied by airless spray nozzles. The Technical officers also inspect the blasted strakes before the primer paint is applied.      
  3. ANCHOR CABLES RANGING AND CALIBRATION                                                                                                       Both the anchors along with their cables are lowered into the dock bottom and the chains are ranged to enable the chains are ranged to enable the chains to be calibrated. The diameters of the links are checked and noted and shown to the surveyor. Links on any chain length which have wasted are discarded by renewing the chain length. The ship always carries one spare length as per regulations. This length is attached to either the port or starboard anchors. It is a good practice to turn the chains end to end at each drydocking so that the link wear is uniform.                                                                                         
  4. CLEANING AND PAINTING OF CHAIN LOCKER                                                                                                            The chain wells are cleaned of mud and accumulated water and painted with a slow drying chlorinated rubber based paint. This work can only be done in dry dock since the anchors and chains are taken out into dry dock.                                                  
  5. BUILDING UP THE HAWSE PIPE CAST STEEL COLLARS AT BOTH ENDS                                                                                                                                                    Due to the frequent rubbing of the chain links on the collars during anchor dropping and heaving up the anchors, the collars get heavily grooved and if neglected can cause damage to the hawse pipes. Hence this work is done during dry docking when the hawse pipes are free of the chains.                                          
  6. ECHO SOUNDER TRANSDUCERS CLEANING AND CHECKING OF WATERTIGHT TERMINAL BOXES                                                                                                        The echo sounder are serviced and the cables are checked for continuity and earth after cleaning the connections in the terminal box. The transducer plates are cleaned and a coat of fish oil applied on the transducers.                                                
  7. SAL LOG OR DOPPLER SPEED LOG                                                                                                                                  The ship may be fitted with a Doppler speed log or a Sal log in the case of older ships. These equipments are to be serviced and calibrated. The dry docks provides the best situation for verification since any transducers fitted underwater can be thoroughly checked and renewed if they are faulty.                     
  8. SACRIFICIAL ZINC ANODES OR IMPRESSED CURRENT SYSTEM                                                                                                                                                                  All zinc sacrificial anodes are to be renewed. Most of them would be completely wasted. If any un-wasted anodes are found they are not of good quality and hence must be renewed. The number of zinc anodes should not be reduced as they are calculated as a total quantity of zinc to be distributed all over the hull surface especially on the bilge keels, the stern portion and on the rudder, The total mass of zinc used is proportional to wetted surface area of the ship and the mass of the propeller.      If the ship is fitted with an impressed current system then it must be serviced and calibrated.                                                      
  9. SEA CHESTS CLEANING AND PAINTING                                                                                                                          All ships are fitted with at least three sea chests in the machinery space area. They are high sea suction, low sea suction and the emergency fire pump sea suction. Their suction grids are to be dismantled and cleaned. The internal surface of the chest have to be scraped clean of all growth. In case of doubt, the casing plate thickness have to be gauged for thickness and renewed as necessary. After cleaning they are to be painted in accordance with the ships hull painting specification. Zinc anodes in the sea chests are to be renewed.    
  10. SEA SUCTION AND DISCHARGE VALVES OVERHAUL AND SURVEY                                                                                                                                                      All sea suction and discharge valves are to be overhauled at every drydocking. Every alternate dry docking they are surveyed. The air and steam connections to the boxes must be checked and any defects also attended. Many shipping companies also overhaul the main intermediate valves and attached mud filters.                                                                      
  11. SANITARY STORM VALVES OVERHAUL AND THEIR SURVEY                                                                                                                                                                                        All storm valves flaps will be dismantled, their leather washer renewed and defective hinge pins renewed. The soil pipes will be inspected for any signs of excessive corrosion, cracks and necessary renewals carried out. The provision of storm valves is a mandatory requirement under LL Regulations even if the ship is fitted with sewage treatment plant.                                    
  12. DAMAGED PORTIONS OF BILGE KEELS TO BE RENEWED                                                                                  
  13. RUDDER PINTLE CLEARANCES JUMPING CLEARANCE, ANY REPAIRS AND HYDRAULIC TESTING                                                                                                                                                                                    The rudder bottom plug is opened out in dry dock. If accumulated water comes out. It indicates the rudder plating is cracked and hence sea water has found its way into the rudder making it heavy causing the rudder movement sluggish. Hence the location of the damage has to be found out and then suitably repaired. For this, the rudder top plug is opened. The bottom plug refitted and rudder filled up with water through the top plug. The location of the damage will be found out by water seen leaking out from the hole/crack. Suitable repairs can now be carried out and finally, an hydrostatic test can be carried out by filling water into the rudder through a flexible rubber tube fitted at the end of the rubber pipe with the funnel held at the summer load line level. This test proves the tightness of the repair when the rudder internally is subjected to head of water up to summer load line. The internal surface of the rudder is painted by a process of paint displacing the water, whereby the paint resting on the water surface spreads all around internally whilst the water level is being lowered through the bottom plug. This method is called the float coat method using a rubber based paint of lower density and slower drying rate. All paint manufacturers supplying ship's paints make this kind of paint.                                                                 The pintle bush clearance for the top and bottom pintles are to be measured using long feeler gauges. The allowable pintle bush clearance is 15 mm for pintle dia. up to 200mm. For dia. exceeding 200mm the clearance is proportionately increased. If the clearances are excessive the bushes are to be renewed after dismantling the rudder. The clearances are taken at the port, starboard, forward and aft and the maximum of these is the clearance.                                                                                       The rudder drop is measured using the rudder trammel gauge, but many ships are not checking the rudder drop since the verification of jumping clearance gives the same information. The verification of jumping clearance is carried out by comparing the clearance at the jumping bar under the rudder skeg with the clearance at the steering gear X-head. The clearance at the X-head should be more than the jumping clearance to prevent the X-head interfering with the rams and damaging the rams. Jumping clearance can be increased by wear of the rudder pedestal bearings or by the jumping bar falling off the rudder if the welding holding the bar has given way. If the pedestal bearing has worn off the rudder is to be jacked up and the pedestal bearing halves dismantled, the bearing built up by welding and suitably machined.                    
  14. PROPELLER DROP                                                                                                                                                                  The propeller drop is taken or measured at every dry docking irrespective whether the propeller shaft is withdrawn for survey or not withdrawn. In oil lubricated shaft systems the drop is measured by a Vernier poker gauge maintained on board and kept with the C/E. This poker gauge is inserted in the aft seal box through a plug hole provided for the same and measured from top and bottom plugs.                                                           Propeller polishing and repairs if needed. The propeller blades and boss are polished using rotary sand diskers so that the small barnacle growth on the blade surface are polished thereby restoring the original speed. After polishing a coat of fish oil is applied on the blades. All air cavitation pitting craters are filled up utilizing a polymer-based bronze cement and then polished. Frayed and cracked blade ends are built up by brazing utilizing compatible bronze alloy filler rods.                                
  15. PROPELLER SHAFT SURVEY IF DUE                                                                                                                                The propeller shaft is withdrawn for the survey in accordance with the following time intervals;                                                 (a) Shafts seawater lubricated and having lignum vitae or synthetic fibre bushes-every four years.                                                                                                                                        (b) Shafts keyed and oil lubricated with patent seals- every five years.                                                                                                                                                                                              (c) Shafts keyless and oil lubricated with patent seals-every ten years.                                                                                                                                                                                                   By this arrangement ships having keyed propeller shafts with patent oil seals will have their shaft withdrawal and survey every alternate drydocking. Ships having keyless shafts with patent oil seals will have the shaft withdrawal and survey every fourth drydocking. Ships having water lubricated shafts and working in synthetic fibre bushes will have their shaft survey every four years, which may need special dry docking for this survey or they may be able to adjust the dry docking to ensure that they comply with the rule requirements.                                                                                                                                        Conclusion: The drydocking survey report issued by the surveyor attending the dry dock will have the following entries, recordings and suitable notations:                                             (a) Bottom inspection- date of inspection and any correction          work carried out with the specification of work carried out.   (b) Anchor chain calibration readings and any renewals         (c) Sea valves survey                                                               (d) Storm valves survey                                                           (e) Rudder pintle clearances measurement. If bushes are                   renewed it will be recorded.                                                   (f) If rudder pedestal bearing built up and machined it                      should be recorded.                                                                (g) Propeller drop recorded.

Comments

  1. Hi, I visited your website and I really like your website, you have got great information and this website is very useful

    ReplyDelete

Post a Comment

Popular posts from this blog

Load Line & Why it is Important

Merchant ships have a marking on their hull know as the Plimsoll line or the Plimsoll mark, which indicates the limit until which ships can be loaded with enough cargo, internationally, the Plimsoll line on a ship is officially referred to as the international load line. Every type of ship has a different level of floating and the Plimsoll line on a ship generally varies from one vessel to another.  All vessels of 24 meters and more are required to have this Load line marking at the centre position of the length of summer load water line. There are two types of Load line markings:- Standard Load Line marking – This is applicable to all types of vessels. Timber Load Line Markings – This is applicable to vessels carrying timber cargo. These marks shall be punched on the surface of the hull making it visible even if the ship side paint fades out. The marks shall again be painted with white or yellow colour on a dark background/black on a light background.  The comp

Difference Between A, B & C-Class Divisions?

IMO Symbol A Class Division  IMO Symbol B Class Division  SOLAS has tables for structural fire protection requirement of bulkheads and decks. The requirements depend on the spaces in question and are different for passenger ships and cargo ships. The Administration has required a test of a prototype bulkhead or deck in accordance with the Fire Test Procedures Code to ensure that it meets the above requirements for integrity and temperature rise. Types of Divisions: "A" Class "B" Class "C" Class "A" Class: "A" class divisions are those divisions formed by bulkheads and decks which comply with the following criteria: They are constructed of steel or equivalent material They are suitably stiffened They are constructed as to be capable of preventing the passage of smoke and flame to the end of the one-hour standard fire test. they are insulated with approved non-combustible materials such that the average tempera

Gravity Disc

Oils containing water can only be de-watered in a perfect manner if the bowl is accurately adjusted to the difference in densities of oil and water. The gravity disc with proper inner diameter i.e. with the diameter that corresponds to the difference in densities of the oil-water mixture to be treated should, therefore, be inserted in the bowl, This disc can be chosen from the set of disc provided with the separator. The inner diameter of the disc to be chosen can be determined by:  Calculation   Experiment The general rule is : Small diameter gravity disc when treating heavy oil Large diameter regulating ring when treating light oil Determining the size of gravity disc by calculation: For a given separating temperature, the inner diameter of the gravity disc and if the desired density of the oil can be determined from the diagram, provided that the density of the oil at a temperature ranging 15℃ and 90℃ is known. For example; Given: Density of oil at 20℃            ρ oil